Fast Facts
- Scope: 110V Battery Bank and Charger Installation
- For: Bilin(33/11kV,10MVA ) Substation
- Purpose: to supply substation
- Timeline: 202days/1616hours
- Outcome: More reliable electricity distribution in Myanmar, fewer outages for community and key tourism assets
110V Battery Bank and charger Installation- Bilin Township
110V Battery Bank and charger Installation was executed to provide a robust, dedicated feeder that improves voltage stability and reduces interruptions across Mawlamyine Township in Mon State. . Delivering a dedicated feeder isolates critical loads from upstream disturbances, improving reliability while enabling future load growth.
Planning, Schedule, and Risk Controls
The project achieved completion in 202 calendar days and 1616 total work hours.
- Weather-aware construction sequencing to avoid monsoon disruptions
- Daily coordination meetings and toolbox talks to maintain quality and safety
These controls ensured the 110V Battery Bank and Charger Installation hit time, cost, and quality targets without compromising HSE (health, safety, environment) standards.
Turnkey Scope & Technical Works
Executed as a full turnkey EPC, the scope covered end-to-end activities:
Survey & Design
Material Transport
Installation
Testing & Commissioning
Mechanical completion, punch-list clearance, insulation resistance checks, line patrolling, sectional energization, and as-built documentation.
All materials and workmanship complied with national and international quality standards, assuring long-term performance and maintainability for the electricity distribution in Myanmar grid.
- Fewer outages due to upstream faults or switching operations
- Improved voltage profile during peak pilgrimage periods
- Higher resilience to seasonal weather impacts
- A clearer maintenance window for utility crews without disrupting essential tourist operations
These improvements ripple outward—better reliability for local businesses, accommodation, and transport, and a more stable platform for future electrification initiatives.
Health, Safety, and Environmental (HSE) Performance
Construction adjacent to public roads and pilgrimage routes required stringent HSE measures: traffic coordination during stringing, barricading around foundation works, fall-protection for work-at-height, and live-network proximity procedures. Daily HSE briefings and documented permits-to-work underpinned safe execution throughout this project.
Outcomes and Handover
With testing and commissioning complete, the line entered service on schedule. The utility received a full handover package—test reports, material certificates, relay settings, and as-built drawings—supporting smooth operations and lifecycle maintenance.
Community and system benefits:
- More reliable supply to Bilin Township households and services
- Stable power for Bilin Township
- Reduced technical losses and improved operational flexibility for the utility
- Stronger backbone for regional growth in Mon State
Explore additional powerline works on the Projects page.