The Goal

To increase electricity access in Yangon region and to make better electrification system.

days
0
man hours
0

Location

Kyonkan Village, Kyauktan Township, Yangon Region, Myanmar

What we did

We mainly constructed the electrical switchbay foundation and control building to access the distribution line in substation. We do the installation for all civil, electrical and mechanical work for the whole substation compound especially for Control Building, Switchyard, Compound Fence and Switchyard fencing. Our construction period is during the raining season so we have some difficulties but we accomplished the projects to meet with quality and time.

End Results

Meet the project time frame as well as both national and international quality standard. Handing over to YESE (Yangon Electricity Supply Corporation)